Alex → Sam
Subject: Payment flow: revised delivery target and next update
Hi Sam,
We found an issue in the final checks: some payment confirmations are not displaying correctly. We won’t be able to deliver the test build on Thursday, 24 September, as planned.
The homepage is ready, but the payment flow needs another round of testing. We’re aiming to deliver the test build on Monday, 28 September, provided the checks pass. This is a target, not a confirmed delivery date.
I’ve asked Nina to help with testing. I’ll send an update by 3 p.m. SGT on Friday, 25 September, even if the issue is still unresolved. If your demo cannot move, we can show the homepage and leave payments out.
I’m sorry for the disruption. Please let me know whether a homepage-only demo would be useful.
Best, Alex